On August 12, 2014, GE Yamal project KOM meeting was held in NFPT international product development department, GE's senior purchasing manager Xiao Bo and SQE Jonas Wu, NFPT's operation director Lu Jie, project manager Dong Jianjian, sales manager Li Changxi, engineers Yang Huihong, Yao Jin, Xingxin, Wang Xiujuan, and Ji Tingting participated in this meeting. jonas chaired this meeting. The meeting mainly included NFPT company introduction, showroom, production workshop, laboratory tour, project team members introduction, project plan review, order and project technical documents review and key points analysis.
GE Senior Procurement Manager Xiao Bo introduced the significance of the project; listened to NFPT's report on the progress of the whole project and the composition of the project members; put forward requirements for the project plan: the project schedule needs to be refined, the nodes to determine the relevant person in charge, and the high-risk nodes should be considered as a response to the program and the cushion; put forward requirements for the quality of the whole project: the management of the sub-suppliers should be strengthened, and the first-tier suppliers should be 100% responsible for the second-tier suppliers. Jonas led the NFPT project team members to review the key project documents, including PO, ordering sheet, TRS, QRL, painting specification, instrumentation specification and so on. Jonas led the NFPT project team members to review the key documents of the project, including: PO, ordering sheet, TRS, QRL, painting specification, instrumentation specification, etc., and interpreted the key points; especially pointed out that we should determine the collector and box suppliers as soon as possible, and submit the Welding book as soon as possible; and requested NFPT to start to prepare for the CU_TR, Fire safety certification of the project as soon as possible. Manager Dong Jianjian said that NFPT project team members will study the project documents, refine the plan, deepen the design, and work overtime to ensure the quality and delivery. Director Lu Jie emphasized the significance of this project to NFPT and said that NFPT will integrate quality resources to ensure the implementation of this project.